Solo Resources is pleased to announce that we have concluded a contract with Akobo Minerals for a gold plant in Ethiopia. The plant in short:
- The plant is designed to process 10 tons of solids per hour, with the possibility of upgrading to 20 tons per hour;
- The plant incorporates crushing, milling, gravity gold recovery and treatment, followed by a CIL plant and cyanide destruction;
- The plant will be tailored to process the highly gold rich Segele Mine ore;
- Solo’s responsibilities include, design, procurement, delivery, as well as site installation and commissioning supervision;
- Commissioning expected to start by end of first quarter 2023;
Jørgen Evjen, CEO of Akobo Minerals, stated: “We have consistently delivered on all the important milestones of recent years, but this is the most important so far. With this agreement, I am confident that we will be produce gold from the Segele mine for many years to come, and that with a solid cash flow. “